# Swimming pond gravel preparation worksheet

Print a working copy and fill the spaces by hand, or edit the Markdown version. Keep all three parts with the material specification and delivery records. This is a job-planning record, not a gravel specification, laboratory test or installation approval.

Version: 18 September 2026. These are questions to agree for your project; no universal grade, layer depth, rinse count or wash requirement is supplied.

## 1. Agree the material before ordering

Use one record for one material, layer or delivery lot. The designer supplies the acceptance requirements; the supplier documents the offered material. Leave an unresolved item open before ordering.

### Identity and intended job

- Project / location / country: ________________________________________
- Prepared by / date / drawing revision: ________________________________________
- Material role and exact zone or layer on the drawing: ________________________________________
- Supplier / product / quarry or other source reference: ________________________________________

### Specification and supporting evidence

Ask what the size label and “washed” description mean for this order. Record the agreed requirements and evidence rather than filling in limits from a different pond.

- Required grading / units / supplier grading report reference: ________________________________________
- Allowed fines / assessment method / person setting the requirement: ________________________________________
- Composition or nutrient-release evidence required by designer / report and sample reference: ________________________________________
- Layer dimensions / quantity / units / quantity calculation reference: ________________________________________
- Compatibility: liner protection, distribution openings, supports and planting / accepted detail reference: ________________________________________
- Who accepts the specification / decision date / unresolved questions: ________________________________________

## 2. Check the sample and the delivery

Keep the order, sample record and delivery ticket together. A photograph or settled-water observation records appearance; it does not establish chemistry, treatment performance or swimming-water safety.

### Sample and delivery match

- Sample ID / source / date / how selected: ________________________________________
- Delivery date / ticket / lot or load reference: ________________________________________
- Observed dust, loose sediment, debris or difference from sample / photo reference: ________________________________________
- Checks required by specification / results / reviewer: ________________________________________
- Decision: accept / hold / return / prepare as agreed — who decided and why?: ________________________________________

### Preparation, only when required

Agree the method before starting. Extra rinsing is not an automatic remedy for the wrong material. Do not substitute a visual rinse result for the acceptance requirements on part 1.

- Preparation required? Yes / no / unresolved — instruction reference and decision-maker: ________________________________________
- Agreed method / people and equipment / responsible person: ________________________________________
- Work area / separate storage / route to the bed / protection of finished work: ________________________________________
- Water supply and expected amount, if used / units / basis of estimate: ________________________________________
- Wash-water and sediment collection / destination / local permission or acceptance reference: ________________________________________

Resolve the dirty-water route before washing. Do not assume a drain, ditch, soil area or the pond is an acceptable outlet. Ask the responsible contractor to check the applicable local requirements.

## 3. Record effort and access before closing the job

If preparation is required, a small agreed work batch can help you estimate the remaining handling. Record the conditions; one batch is a planning observation, not a guaranteed production rate.

### Handling and preparation allowance

- Batch amount and units / date / method used: ________________________________________
- People involved / elapsed time / total person-hours: ________________________________________
- Time included: setup / moving / preparation / clean-up — specify: ________________________________________
- Water used, if measured / units; otherwise mark estimate or unknown: ________________________________________
- Remaining quantity / expected hours and basis / equipment or waste costs and currency: ________________________________________
- Access, weather, storage or delivery constraints that may change the allowance: ________________________________________

### Placement and future maintenance

Confirm the specified liner protection and service openings before covering work. Keep covers reachable and a route for future tools, removed material and replacement components.

- Installed zone / quantity / drawing and photo references / accepted deviations: ________________________________________
- Service opening and working space / hose or tool route / planting clearance checked by: ________________________________________
- Cleaning method and trigger from system instructions / removed-water and sediment route: ________________________________________
- Outstanding issue / named person / next action / date; who accepted placement?: ________________________________________

## Sources and scope

- [IOB Common Essentials](https://iob-ev.com/en/common-essentials/): Association principles on material pollution and phosphorus inputs; no gravel grade or test limit supplied.
- [Aquascape wetland system instructions](https://www.aquascapeinc.com/instructions/wetland-system): A named-system example of component compatibility and service access; its sizes and routine are not transferred to other designs.
- [Environment Agency: pollution prevention for businesses](https://www.gov.uk/guidance/pollution-prevention-for-businesses): England-specific guidance on contaminated water and drainage; local requirements govern the actual destination.

Sources checked 18 September 2026.

## Related guides

- [Filtration and media decisions](/guides/swimming-pond-filtration)
- [Construction stages and inspections](/guides/planning-a-swimming-pond-build)
- [Liner protection and compatibility](/guides/swimming-pond-liners)
- [Maintenance planning](/guides/swimming-pond-maintenance)